Advert
Advert
Main content

Guide to Restumping

» Brought to you by

Re-stumping - also known as re-blocking in Victoria- is the process whereby timber stumps that support a house are replaced due to being rotted and defective.

It's a multi-million dollar business in Australia and unfortunately very few people are aware of the many potential pitfalls in this trade. Problems reported to Archicentre include contractors asking for advance payments then disappearing, unexpected damage to walls, windows and plumbing, work having to be redone, squeaking floors, and floors which are more crooked after having been stumped. To ensure you aren't the victim of unscrupulous operators, check the condition of the existing stumps before you do anything else.

1. Select your stumps


The first decision to make is to choose the most suitable type of new stumps.

Selection of stumps - Victoria


• Rot-resistant timber stumps, like Victorian red gum are still quite commonly used. Their advantage is that they are still sometimes 10% cheaper than concrete, and although they have the disadvantage of limited life expectancy, this will not affect occupants living in the house for less than 20 years.
• Perhaps the biggest disadvantage is that timber stumps cannot be as firmly secured to the bearers as concrete stumps so that re-levelling may not be quite as accurate.

Concrete stumps


• Concrete stumps are available in several types.
• The concrete stump with the most positive form of connection is the one with a 10mm diameter threaded rod at the top secured with a poured concrete pad footing. The threaded rod allows the stump to be bolted to the floor frame preventing both upward and downward movement. The concrete pad will provide protection against long term footing settlement.
• A further advantage is that by tightening the nut after the concrete pad has set, and by partially cutting the bowed bearers at their high points, high spots in the floor can be pulled down.
• Concrete stumps will last indefinitely except in extremely damp conditions where the metal reinforcement in the stump rusts and expands, causing weakness. This also applies in Queensland.

Selection of Stumps - Queensland


• Stumps in the past were made of 300mm diameter ironbark or similar rot-resistant timber. Now CCA (copper chrome arsenate) treated pine, or concrete stumps are used.
• The most positive form of connection to the bearer is a bracket fixed to the stump by a coach screw or bolt. The other end of the bracket is anchored to the bearer by a threaded end and nut. This is also a positive form of stump/bearer connection.
• In cases where the ground is unstable (soft), a concrete footing is sometimes poured.
• Because of high wind stresses, anchor bolts are required at each corner of a Queensland house, around the perimeter every four metres and under bracing walls. These bolts are also needed in high wind areas of Victoria.

2. Selecting the Right Contractor


Having chosen the most appropriate stumping system, extreme care should be taken in selecting a reliable and experienced contractor.

The contractor should have enough hydraulic jacks to lift the building in one or two sections. Generally one jack is required for each stump as there are about 80 stumps in an average 150 sq. metre (16 square) timber house, less for other types of housing like brick veneer (approx. 60). If too few jacks are used, the house will need to be lifted in several sections, which will cause severe and costly damage to plaster-work and framing

In choosing the contractor, the following points should be made clear when obtaining quotes. These points should also form the basis of a contract between you and the re-blockers:


• The type of stumps (and pads, if appropriate) to be used.
• The spacing of stumps.
• That on completion the floors will be brought reasonably back to level, say within 10mm.
• That the work will be in accordance with the relevant building regulations.
• That a council building permit will be obtained.
• The agreed cost.
• The start and expected completion date.
• That if floorboards must be removed, to what condition the floor will be reinstated and whose responsibility it is to remove and replace coverings.

When comparing quotations from several contractors, ensure that they all include the same items. The lowest price may only be indicative of a lesser number and poor choice of stumps, which may spell disaster in the long term.

After receiving the quotes, check the bona fides of the contractors by asking them to give you the names and telephone numbers of one or two people they have recently done work for. Check that these people are happy with the work, and you may even ring the local council's Building Surveyor in the area where work was carried out and make sure that the council was satisfied with the job.

3. Monitor the work after it has commenced

After the work has commenced, it is essential that it be supervised carefully. The most common faults are:
• Floors not properly re-leveled. This should be thoroughly checked with a spirit level, or preferably, a dumpy level.
• Stumps not being securely fixed to bearers, (this may eventually result in a noisy floor).
• Stumps not positioned directly underneath the joining of two bearers.
• Stumps not centrally located over pads, where pads are used.
• Failure to provide ant caps between stumps and bearers.

When new stumps have been installed and the jacks removed, the holes should be back filled with well-compacted earth.

The final payment to the contractor should be made only after all work has been completed according to the contract and has been found to be satisfactory.

Remember, the best way of avoiding expensive problems is to be aware of them before you purchase your house or before you undertake repairs and renovations. You can also seek advice from organisations such as Archicentre who have carried out thousands of home inspections for home owners and prospective buyers. A home inspection can help you to make a realistic appraisal of the property before you decide to buy, renovate or repair.

 
 

Sign Out

Join the Conversation

Please note, LifeStyle cannot respond to all comments posted in our comments feed. If you have a comment or query you would like LifeStyle to respond to, please use our feedback form.

4 comments
Please login to comment
Posted by Bruce195 • 16w ago • Report
I have been restumping houses for 20years, the foundations should be the start of any renovation. A little extra cost at the start can save a lot of tears a few year done the track.
www.ablereblocking.com.au
Posted by Kerri204 • 17w ago • Report
We own a restumping business in Melbourne, www.djbakerandson.com.au and are often surprised how often people neglect the foundations of their home, especially when they make renovations. They are your houses legs people :)
Posted by Kenny18 • 24w ago • Report
Restumping can be a difficult process and there are many options for replacement materials. You make some great about what to look for when restumping. Unfortunately last time we did this on my home, we didn't re-level the floors properly. It caused major damage and a lot of inconvenience. I hope others take your advice.

Kenny Jarden | http://www.budgetreblocking.com.au
Posted by Kenneth45 • 46w ago • Report
thanks for the post! i'm really considering restumping for my house. glad to have read this post. for other home owners, you may want to check this out as well - http://qldhouserestumping.com.au/reasons-might-raise-house/